Sign In  |  Register  |  About San Rafael  |  Contact Us

San Rafael, CA
September 01, 2020 1:37pm
7-Day Forecast | Traffic
  • Search Hotels in San Rafael

  • CHECK-IN:
  • CHECK-OUT:
  • ROOMS:

Ero Copper's Tucumã Project Achieves Major Milestone at Over 70% Physical Completion - On Track for First Copper Production in H2 2024

VANCOUVER, British Columbia, Oct. 19, 2023 (GLOBE NEWSWIRE) -- Ero Copper Corp. (TSX: ERO, NYSE: ERO) (the “Company”) is pleased to provide an update on the excellent progress being made at the Company's Tucumã Project (the "Project").

Since commencing site works in 2022, all engineering, procurement and construction activities for the Project remain on schedule for first copper concentrate production in H2 2024. Total direct Project capital expenditures remain in line with current guidance of approximately $305 million. Project development highlights include:

  • Construction: Physical construction of the Project is now 70% complete
    • Significant advancement in mine pre-stripping, with first sulphide ore on track to be reached in early November
    • All earthworks now completed, including the water storage reservoir, site drainage and run-of-mine stockpiles
    • Over 15,000 cubic meters of concrete poured (over 65% complete), concluding all major foundation requirements for the Project
    • Steel structure pre-assembly and erection tracking ahead of schedule with approximately 1,000 tonnes of steel already in place
    • Key pieces of processing equipment arrived on site with installations either concluded or ongoing, including the primary crusher, ball mill, secondary and tertiary crushers, vibrating screen decks and flotation cells
    • Main substation installed on site, primary e-room commissioned, and approximately 16 kilometer power line construction tracking ahead of schedule; tie-in to national grid power expected during Q4 2023 
    • Platework, piping and electrical cabling all commenced ahead of schedule

  • People & Safety: Peak construction workforce successfully mobilized on the Project
    • Approximately 1,750 third-party contractors and employees working on site
    • To date, there have been no lost-time injuries on the Project, with approximately two million hours of work completed since 2022

  • Commissioning: The Company remains on track to initiate the first phase of process plant commissioning by year-end and commence operations in H2 2024

Commenting on the progress, David Strang, Chief Executive Officer, said "First and foremost, I would like to congratulate each and every one of the approximately 1,750 people on site on the remarkable progress to date, and most importantly, for their dedication in achieving nearly two million hours of work without a lost time injury. With over 70% of the physical work completed, critical pieces of infrastructure in place or nearing completion, and main equipment installations progressing according to plan, we are confident that a major inflection point for the Project has been reached.

"As we continue to meet our construction milestones, we are turning our attention on site to piping, electrical and instrumentation installation - an exciting time for any Project. We are focused on executing the first phase of the commissioning schedule prior to year-end to ensure a successful ramp-up and achievement of commercial production in the second half of 2024."

Advancement of pre-stripping with first sulphide ore expected November 2023.

Figure 1: Advancement of pre-stripping with first sulphide ore expected November 2023.

Installation of the Ball Mill for the Project.

Figure 2: Installation of the Ball Mill for the Project.

Flotation cells and tailings thickener foundation.

Figure 3: Flotation cells and tailings thickener foundation.

Installation of the primary crusher.

Figure 4: Installation of the primary crusher.

Completed water reservoir.

Figure 5: Completed water reservoir.

Electrical substation prepared for final tie-in to the national grid.

Figure 6: Electrical substation prepared for final tie-in to the national grid.

Project laydown area for pre-assembly and steel storage.

Figure 7: Project laydown area for pre-assembly and steel storage.

ABOUT ERO COPPER CORP

Ero is a high-margin, high-growth, low carbon-intensity copper producer with operations in Brazil and corporate headquarters in Vancouver, B.C. The Company's primary asset is a 99.6% interest in the Brazilian copper mining company, Mineração Caraíba S.A. ("MCSA"), 100% owner of the Company's Caraíba Operations (formerly known as the MCSA Mining Complex), which are located in the Curaçá Valley, Bahia State, Brazil and include the Pilar and Vermelhos underground mines and the Surubim open pit mine, and the Tucumã Project (formerly known as Boa Esperança), an IOCG-type copper project currently under construction in Pará State, Brazil. The Company also owns 97.6% of NX Gold S.A. ("NX Gold") which owns the Xavantina Operations (formerly known as the NX Gold Mine), comprised of an operating gold and silver mine located in Mato Grosso, Brazil. Additional information on the Company and its operations, including technical reports on the Caraíba Operations, Xavantina Operations and Tucumã Project, can be found on the Company's website (www.erocopper.com), on SEDAR (www.sedar.com), and on EDGAR (www.sec.gov). The Company’s shares are publicly traded on the Toronto Stock Exchange and the New York Stock Exchange under the symbol “ERO”.

FOR MORE INFORMATION, PLEASE CONTACT

Courtney Lynn, SVP, Corporate Development, Investor Relations & Sustainability
(604) 335-7504
info@erocopper.com

CAUTION REGARDING FORWARD LOOKING INFORMATION AND STATEMENTS

This press release contains “forward-looking statements” within the meaning of the United States Private Securities Litigation Reform Act of 1995 and “forward-looking information” within the meaning of applicable Canadian securities legislation (collectively, “forward-looking statements”). Forward-looking statements include statements that use forward-looking terminology such as “may”, “could”, “would”, “will”, “should”, “intend”, “target”, “plan”, “expect”, “budget”, “estimate”, “forecast”, “schedule”, “anticipate”, “believe”, “continue”, “potential”, “view” or the negative or grammatical variation thereof or other variations thereof or comparable terminology. Forward-looking statements may include, but are not limited to, statements with respect to achieving first sulphide ore and the expected timing of reaching first sulphide ore, installation of main equipment, including tie-in of power line to national grid, commissioning and first concentration production; the estimated Project capital to be spent; and any other statement that may predict, forecast, indicate or imply future plans, intentions, levels of activity, results, performance or achievements.

Forward-looking statements are not a guarantee of future performance. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Forward-looking statements involve statements about the future and are inherently uncertain, and the Company’s actual results, achievements or other future events or conditions may differ materially from those reflected in the forward-looking statements due to a variety of risks, uncertainties and other factors, including, without limitation, those referred to herein and in the AIF under the heading “Risk Factors”.

The Company’s forward-looking statements are based on the assumptions, beliefs, expectations and opinions of management on the date the statements are made, many of which may be difficult to predict and beyond the Company’s control. In connection with the forward-looking statements contained in this press release and in the AIF, the Company has made certain assumptions about, among other things: continued effectiveness of the measures taken by the Company to mitigate the possible impact of COVID-19 on its workforce and operations; favourable equity and debt capital markets; the ability to raise any necessary additional capital on reasonable terms to advance the production, development and exploration of the Company’s properties and assets; future prices of copper, gold and other metal prices; the timing and results of exploration and drilling programs; the accuracy of any mineral reserve and mineral resource estimates; the geology of the Caraíba Operations, the Xavantina Operations and the Tucumã Project being as described in the respective technical report for each property; production costs; the accuracy of budgeted exploration, development and construction costs and expenditures; the price of other commodities such as fuel; future currency exchange rates and interest rates; operating conditions being favourable such that the Company is able to operate in a safe, efficient and effective manner; work force continuing to remain healthy in the face of prevailing epidemics, pandemics or other health risks (including COVID-19), political and regulatory stability; the receipt of governmental, regulatory and third party approvals, licenses and permits on favourable terms; obtaining required renewals for existing approvals, licenses and permits on favourable terms; requirements under applicable laws; sustained labour stability; stability in financial and capital goods markets; availability of equipment; positive relations with local groups and the Company’s ability to meet its obligations under its agreements with such groups; and satisfying the terms and conditions of the Company’s current loan arrangements. Although the Company believes that the assumptions inherent in forward-looking statements are reasonable as of the date of this press release, these assumptions are subject to significant business, social, economic, political, regulatory, competitive and other risks and uncertainties, contingencies and other factors that could cause actual actions, events, conditions, results, performance or achievements to be materially different from those projected in the forward-looking statements. The Company cautions that the foregoing list of assumptions is not exhaustive. Other events or circumstances could cause actual results to differ materially from those estimated or projected and expressed in, or implied by, the forward-looking statements contained in this press release. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.

Forward-looking statements contained herein are made as of the date of this press release and the Company disclaims any obligation to update or revise any forward-looking statement, whether as a result of new information, future events or results or otherwise, except as and to the extent required by applicable securities laws.

CAUTIONARY NOTES REGARDING MINERAL RESOURCE AND MINERAL RESERVE ESTIMATES

Unless otherwise indicated, all reserve and resource estimates included in this press release and the documents incorporated by reference herein have been prepared in accordance with National Instrument 43-101, Standards of Disclosure for Mineral Projects (“NI 43-101") and the Canadian Institute of Mining, Metallurgy and Petroleum (the “CIM”) — CIM Definition Standards on Mineral Resources and Mineral Reserves, adopted by the CIM Council, as amended (the “CIM Standards”). NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. Canadian standards, including NI 43-101, differ significantly from the requirements of the United States Securities and Exchange Commission (the “SEC”), and reserve and resource information included herein may not be comparable to similar information disclosed by U.S. companies. In particular, and without limiting the generality of the foregoing, this press release and the documents incorporated by reference herein use the terms “measured resources,” “indicated resources” and “inferred resources” as defined in accordance with NI 43-101 and the CIM Standards.

Further to recent amendments, mineral property disclosure requirements in the United States (the “U.S. Rules”) are governed by subpart 1300 of Regulation S-K of the U.S. Securities Act of 1933, as amended (the “U.S. Securities Act”) which differ from the CIM Standards. As a foreign private issuer that is eligible to file reports with the SEC pursuant to the multi-jurisdictional disclosure system (the “MJDS”), Ero is not required to provide disclosure on its mineral properties under the U.S. Rules and will continue to provide disclosure under NI 43-101 and the CIM Standards. If Ero ceases to be a foreign private issuer or loses its eligibility to file its annual report on Form 40-F pursuant to the MJDS, then Ero will be subject to the U.S. Rules, which differ from the requirements of NI 43-101 and the CIM Standards.

Pursuant to the new U.S. Rules, the SEC recognizes estimates of “measured mineral resources”, “indicated mineral resources” and “inferred mineral resources.” In addition, the definitions of “proven mineral reserves” and “probable mineral reserves” under the U.S. Rules are now “substantially similar” to the corresponding standards under NI 43-101. Mineralization described using these terms has a greater amount of uncertainty as to its existence and feasibility than mineralization that has been characterized as reserves. Accordingly, U.S. investors are cautioned not to assume that any measured mineral resources, indicated mineral resources, or inferred mineral resources that Ero reports are or will be economically or legally mineable. Further, “inferred mineral resources” have a greater amount of uncertainty as to their existence and as to whether they can be mined legally or economically. Under Canadian securities laws, estimates of “inferred mineral resources” may not form the basis of feasibility or pre-feasibility studies, except in rare cases. While the above terms under the U.S. Rules are “substantially similar” to the standards under NI 43-101 and CIM Standards, there are differences in the definitions under the U.S. Rules and CIM Standards. Accordingly, there is no assurance any mineral reserves or mineral resources that Ero may report as “proven mineral reserves”, “probable mineral reserves”, “measured mineral resources”, “indicated mineral resources” and “inferred mineral resources” under NI 43-101 would be the same had Ero prepared the reserve or resource estimates under the standards adopted under the U.S. Rules.

Photos accompanying this announcement are available at

https://www.globenewswire.com/NewsRoom/AttachmentNg/bf0a1d58-d5bf-4ff3-bef4-ad657fb9c8c4

https://www.globenewswire.com/NewsRoom/AttachmentNg/d06db9f7-a60e-4afb-b1ca-3fa2ea2b3ec1

https://www.globenewswire.com/NewsRoom/AttachmentNg/6743d8e1-6e8d-480e-81a9-2a82a7142dee

https://www.globenewswire.com/NewsRoom/AttachmentNg/3d6a5699-fac7-4d6c-bc49-45ee13cc1b3f

https://www.globenewswire.com/NewsRoom/AttachmentNg/d58d259e-2a0b-4c01-9002-448c4e60e219

https://www.globenewswire.com/NewsRoom/AttachmentNg/de1a8a0f-41dd-4442-8307-f29b6555e723

https://www.globenewswire.com/NewsRoom/AttachmentNg/5b843529-65da-4973-9d73-edc39645bf15


Primary Logo

Data & News supplied by www.cloudquote.io
Stock quotes supplied by Barchart
Quotes delayed at least 20 minutes.
By accessing this page, you agree to the following
Privacy Policy and Terms and Conditions.
 
 
Copyright © 2010-2020 SanRafael.com & California Media Partners, LLC. All rights reserved.